Scope of work : Redesign To Reconstruct concrete structure, Fountain raft, water tanks under ground, removal of Tiles, Ground Foundation, Slabs. Walls, columns, Beams

Equipments & tools: Generators, Water, Diesel Tankers tankers, Dbs cables pumps, core machines, wire cutting machines, concrete cutting machines, floor saw machines, chain saw, Scanning concrete, Radar Scanner, demolition excavators, mobile cranes shovel, bob cats forklift, trailers, trucks 40 numbers of manpower including safety officer Engineer, Foreman, flag man, riggers.

WEM always leave a positive impact when it comes to Quality of services and Time frame agreed by both parties which put us in a very good condition for any future works with our customers Or potential ones.